Contains 270 Results:
"Responsibility For Hardware Performance", 1983-09-15
Item — Box: 3, Folder: 10
Abstract
There is a note written at the top of the report, which says, "MDAC response to issues placed on the table by Abe on July 15 at HB."
Dates:
1983-09-15
"Basic PAM-D Price Increase Agreement Breakdown" with a note attached that is addressed to Richard, from Mike, 1979 - 1985-06
Item — Box: 3, Folder: 10
Dates:
1979 - 1985-06
McDonnell Douglas Astronautics Company, F. B. Alexander, Manager - Contracts, SPace Programs, Memo entitled, "NASA/MDC SSUS-D Agreement, MDAC-WD-76-185L; Ceiling Price Increase," "Revision C To The NASA/MDC SSUS-D Agreement MDAC-WD-76-158L," & "Annex C Price Adjustment" , 1976-11-24 - 1984-01-26
Item — Box: 3, Folder: 10
Dates:
1976-11-24 - 1984-01-26
"SSUS-D, PAM-D Agreement", 1976-11-15 - 1976-11-24
Item — Box: 3, Folder: 10
Dates:
1976-11-15 - 1976-11-24
McDonnell Douglas Corporation, "Airborne Support Equipment (ASE) 1983 Estimate (Cost - Dollars In Millions)" & "PAM-D Total Program Profit Analysis (Including Ceiling Price Increase) (Dollars In Millions)", 1983-05-01
Item — Box: 3, Folder: 10
Dates:
1983-05-01
"MDAC/NASA Technical Monitoring Agreement For The PAM-DII Perigee Kick Stage System Development", 1983-01-25 - 1983-02-23
Item — Box: 3, Folder: 10
Dates:
1983-01-25 - 1983-02-23
"NASA/MDAC Agreement For Technical Monitoring Of PAM-DII Development "Draft'", 1984-02-08
Item — Box: 3, Folder: 10
Dates:
1984-02-08
Lewis L. McNair, "3. Status Of Technical Monitoring Agreements", 1983-10-25 - 1984-04-05
Item — Box: 3, Folder: 10
Dates:
1983-10-25 - 1984-04-05
"PAM Presentations Made To NASA By MDAC", 1977-09 - 1982-09-02
Item — Box: 3, Folder: 10
Dates:
1977-09 - 1982-09-02
"Appendix A" for PAM-D & PAM-DII with an attached sheet of notes, 1983-01 - 1983-12
Item — Box: 3, Folder: 10
Dates:
1983-01 - 1983-12